Subcontract Closeout: Final Release, Retainage, and Lien Waivers
The work is usually the part you can see coming. The money often goes wrong at the end. The last 10 percent can sit for months, the final release can waive claims you did not know you were giving up, and the lien waiver form can arrive with the last check. This post covers the three documents that decide when you are paid in full: the retainage terms, the final release, and the lien waiver. This is general information, not legal advice. Your subcontract and your prime's terms control.
Two layers of retainage
Retainage means money held back until a condition is met. On a federal job there are two layers, and they are not the same thing.
- Government to prime. On a fixed-price construction contract, the clause at FAR 52.232-5, Payments under Fixed-Price Construction Contracts, lets the contracting officer retain up to 10 percent of a progress payment if satisfactory progress is not being made. When the work is substantially complete, the contracting officer may keep an amount it considers adequate to protect the government and must release the rest.
- Prime to subcontractor. The same clause says the prime's progress-payment request does not include amounts the prime intends to withhold from a subcontractor under the subcontract's terms. In other words, the government's clause does not set your retainage. Your subcontract does.
The practical point: find the retainage percentage, the point at which it is reduced or released, and the trigger for release in your subcontract. "At closeout" is not a trigger. Get the specific event, such as acceptance of your scope or receipt of your final documents, in writing. For the cash-flow side of this, see how federal subcontractors get paid.
The final release: what you are signing
The government will not make its own final payment until the work is complete and accepted, the contractor submits a properly executed voucher, and the contractor delivers a release of claims. The clause allows the contractor to exclude specific claims, but only claims that are listed in stated amounts. Read FAR 52.232-5, paragraph (h) to see the pattern.
Primes often ask subcontractors for a release too. Before you sign one, check three things:
- Scope. Does the release cover only the payment for this subcontract, or does it release every claim you have against the prime on any job?
- Exceptions. Are open change orders, unpaid retainage, back-charges, or disputed amounts listed by name and dollar amount? If not, they may be waived.
- Timing. Is the release signed before or after your final payment clears? A release that is a condition of the last payment is a larger concession than one that follows it.
If an item is still open, list it in writing with a stated amount. A release that is silent about an open item is the easiest way to lose it.
Lien waivers on federal work
Mechanics' liens generally cannot be placed on federal property. That is why federal construction contracts require a payment bond instead. The Miller Act, 40 U.S.C. § 3133, gives people who furnish labor or material on a bonded federal job a right to sue on the payment bond. The bond, not a lien, is your protection.
Primes still ask for lien waivers, often as a contract condition or because they use one form on every job. Two rules keep you safe:
- Know which kind you are signing. A conditional waiver takes effect only when the payment it covers clears. An unconditional waiver takes effect when you sign it, even if the check never arrives. Do not sign an unconditional waiver until the money is in your account.
- Ask about any lien language that does not fit a federal job. If the form refers to a lien right that does not apply to federal property, ask the prime what the waiver is meant to cover before you sign it.
The 90-day clock starts on your last day
The Miller Act deadlines run from the last day you furnished labor or material, not from the day you were paid or the day the project closed. Under 40 U.S.C. § 3133, a person who has not been paid in full within 90 days after that last day may sue on the payment bond. A person who has a contract with a subcontractor, rather than with the prime, must also give written notice to the prime within the same 90 days.
So keep a dated record of your last day on site and your last delivery of material. If a payment problem comes up, that record starts the clock you need to track. For the bond and insurance a prime will expect you to carry, see bonding and insurance for federal subcontractors.
A closeout checklist before you sign anything
- Get the retainage terms in writing. Percentage, reduction point, and the release trigger.
- Record your last day of labor and your last delivery of material, with dates.
- Send the closeout records your subcontract requires. Final certified payroll, if your contract calls for it, is an example. Keep the copies. The retention rules are in how long to keep certified payroll.
- List open items by name and amount in writing before any final release is signed.
- Confirm the waiver type and whether it is conditional or unconditional. Sign an unconditional waiver only after payment clears.
- Check the paperwork set. The federal subcontract paperwork checklist lists the core forms and records a prime will ask a federal subcontractor to produce.
Your next step
If closeout is coming up on a job you already have, start with the checklist above and send the retainage question to your prime this week, while there is still time to get the answer in writing. If you are new to federal subcontracts, begin with what a federal subcontractor is.
Learn the paperwork. Get connected to the buyers.
Federal Sub Academy teaches the SF 1413, the daily report, and certified payroll step by step. Enrollment is open now — $2,495.95 one time for the full program.
Not ready to enroll? Join the opening list. Hiring subcontractors? See the subcontractor directory.
Get the free paperwork checklist
The core federal subcontract forms and records, on one page. Free, no sign-up.