Bonding and Insurance for Federal Subcontractors: What Primes Require

"Bonding" and "insurance" get used like they are the same thing. They are not. On a federal construction job, the prime posts the payment and performance bonds, and the subcontractor carries insurance. Understanding which is which tells you what you actually have to buy — and what protects you if the prime does not pay.

What the Miller Act requires

On federal construction contracts over $150,000, the prime must furnish two bonds under the Miller Act (40 U.S.C. chapter 31, subchapter III), implemented at FAR 28.102-1:

The bonds are the prime's obligation to the government. You do not post Miller Act bonds on a federal job just because you are a sub.

Do subcontractors need to be bonded?

Not to the government. The prime holds the Miller Act bonds. But two situations still involve bonding for a sub:

Claiming the Miller Act payment bond

If the prime does not pay you, the payment bond is your backstop. The deadlines are firm:

These are outside your normal collection timeline. Calendar them the day you start, not the day you get stiffed. Bond and payment mechanics are covered further in how federal subcontractors get paid.

Insurance the prime will require

This is the part that hits almost every sub. A prime will not let you mobilize without proof of coverage. Typical requirements in a subcontract:

Most primes also require that they be named as an additional insured and that you provide a certificate of insurance (COI) before work starts — with the requirement to keep it current for the life of the job.

Checklist before you sign

  1. Read the insurance section of the subcontract and match every limit to your policy.
  2. Confirm whether the prime requires a bond from you — and price it in.
  3. Ask for the prime's payment bond and confirm it exists for the contract you are on.
  4. Calendar the 90-day notice and one-year suit dates if you are unpaid.
  5. Send a current COI, with the prime as additional insured, before mobilization.

Clause details like these reach you through flow-down clauses, and they are part of why primes vet subcontractors before they hire.

Your next step

Know which document protects you before you need it. Start with how federal subcontractors get paid and flow-down clauses, then work through the federal subcontract paperwork checklist.

Learn the paperwork. Get connected to the buyers.

Federal Sub Academy teaches the SF 1413, the daily report, and certified payroll step by step. Enrollment is open now — $2,495.95 one time for the full program.

Enroll now — $2,495.95 Student sign in

Get the free paperwork checklist

The core federal subcontract forms and records, on one page. Free, no sign-up.

Read the checklist