How to Fill Out a Daily Report on a Federal Construction Contract
The daily report is the running record of the job. Primes and owners read it to see what happened, who was on site, and whether the job is on track. A clean daily report is one of the fastest ways to become the subcontractor a prime wants to keep.
The fields, and what each one means
- Date / report number. Number reports in sequence so nothing goes missing.
- Contractor / contract no. / title and location. Identify the job and your firm unambiguously.
- Superintendent. The lead on site that day.
- AM / PM weather, max / min temperature. Actual conditions. Weather delays and temperature affect schedule — and, later, any claim for delay.
- Work performed today. Location and description, plus each crew: employer, number of workers, trade, and hours.
- Job safety. Whether a safety meeting was held (attach minutes), any lost-time accidents (attach the report), and whether trenching, scaffold, high-voltage, or high work was done.
- Hours totals. Total hours on site that day, plus the cumulative total carried forward from prior reports.
- Remarks. Anything the next reader needs — progress, delays, issues, instructions.
A concrete example
Tuesday, 42°F and rain. You place formwork on the east wall, four workers (2 carpenters, 2 laborers), 32 total hours. A safety meeting was held. You note in remarks that rain stopped work from 1:00 to 3:00 p.m. That one line, written the day it happened, is worth more than a paragraph written a month later when a schedule dispute comes up.
Why accuracy protects you
Record facts, not opinions. Note weather and delays the day they happen. Keep the hours consistent with your certified payroll — the two documents should always tell the same story. Sign every report. If a dispute or claim ever arises, the daily report is often the document that decides it.
Your next step
Take your next job and write the daily report the same day, every day, using the fields above. Make the hours match your payroll. That single habit is the difference between a subcontractor a prime defends and one a prime drops.
Learn the paperwork. Get connected to the buyers.
Federal Sub Academy teaches the SF 1413, the daily report, and certified payroll step by step. Enrollment is open now — $2,495.95 one time for the full program.
Get the free paperwork checklist
The core federal subcontract forms and records, on one page. Free, no sign-up.