Consent to Subcontract Under FAR 52.244-2: When Your Prime Needs Government Approval
Sometimes a prime contractor cannot simply sign you up. On certain federal contracts, the prime has to get the contracting officer's written consent before it places a subcontract. The rule that does this is FAR 52.244-2, "Subcontracts." It does not apply to every federal job, but when it does, it can change how fast you get signed, what the prime has to send to the government, and what you can rely on. Here is how it works in plain English.
What the clause says
FAR 52.244-2 is a clause the government writes into some prime contracts. It defines "consent to subcontract" as the contracting officer's written consent for the prime to enter into a particular subcontract. A "subcontract" under the clause is broad: it includes purchase orders and changes or modifications to purchase orders, not just a long-form agreement. You can read the full clause at acquisition.gov, FAR 52.244-2.
When consent is required
The clause does not require consent for every subcontract. Whether your subcontract needs it depends on the prime's purchasing system and on the type and size of the subcontract:
- No approved purchasing system. If the prime's purchasing system has not been reviewed and approved under FAR part 44, consent is required for any subcontract that is cost-reimbursement, time-and-materials, or labor-hour. A fixed-price subcontract needs consent only if it goes over the threshold in the clause, which is tied to the simplified acquisition threshold (defined at FAR 2.101) or 5 percent of the contract's estimated cost, depending on the agency.
- An approved purchasing system. The prime still needs consent for any subcontracts the contract lists by name in the clause.
- Fixed-price contracts. When the clause is in a fixed-price contract, consent is generally needed only for unpriced contract actions, such as unpriced modifications or delivery orders.
- Exceptions. Subcontracts the government reviewed during negotiations can be listed as exempt from the notice and consent steps.
The practical answer to "can a prime subcontract without approval?" is: sometimes yes. If the clause is not in the contract, the subcontract is under the threshold, the prime has an approved purchasing system, or the subcontract is on the exempt list, consent is not required. Do not assume. Ask the prime which case applies to your subcontract.
What the prime has to send the government
When consent is required, the prime must notify the contracting officer reasonably in advance of placing the subcontract. The notice must describe the supplies or services, the type of subcontract, the proposed subcontractor, and the proposed price. Where other contract provisions require them, it also has to include the subcontractor's certified cost or pricing data and a negotiation memorandum that explains how the price was set.
For a subcontractor, this means you may be asked for pricing support and cost information before you are signed. Expect that request, and keep your cost build-up ready. The clause does not set a fixed number of days for the contracting officer's review, so plan your start date with that uncertainty in mind.
What consent does not mean
Consent is not a government stamp of approval on your subcontract. Under the clause, the contracting officer's consent is not a determination that the subcontract terms are acceptable, that any cost is allowable under the prime contract, or that the prime is relieved of its responsibility to perform the contract. The prime still owns the work and the terms it agreed to.
Two more rules from the clause matter to subcontractors. A subcontract cannot pay on a cost-plus-a-percentage-of-cost basis. And any fee on a cost-reimbursement subcontract is capped by the limits in FAR 15.404-4. If your deal is built on a percentage of cost, read the clause before you agree to it.
What to do before you mobilize
- Ask whether the prime contract includes FAR 52.244-2. Check the clause list in the prime contract, or ask the prime in writing. The clause appears in the contract's list of clauses.
- Ask whether your subcontract needs consent. Get the answer in writing, along with the subcontract type and price the prime will submit.
- Get the effective date in writing. If consent is still pending, do not order materials or staff up on the assumption that it will come through.
- Ask what happens if consent is delayed or denied. The clause does not spell out your rights under your subcontract. That is a term you negotiate with the prime, so make sure it is written down.
- Keep your cost support ready. The prime may need your pricing to write its notice to the government.
Consent is one more gate between a signed intent and a paid start. Subcontracts also depend on the flow-down clauses that carry the prime's obligations into your paper, and on the paperwork checklist a prime will ask you to complete. Primes also look closely at subcontractors before they hand one over; see how primes vet subcontractors.
Your next step
If you are new to federal subcontracts, start with what a federal subcontractor is, then read about the difference between a teaming agreement and a subcontract. A teaming agreement does not start the consent process on its own. The subcontract does.
Learn the paperwork. Get connected to the buyers.
Federal Sub Academy teaches the SF 1413, the daily report, and certified payroll step by step. Enrollment is open now — $2,495.95 one time for the full program.
Get the free paperwork checklist
The core federal subcontract forms and records, on one page. Free, no sign-up.